1000 t/d cement production line

1000 t/d cement production line
Model:1000 t/d
Brand:RP
Origin:Made In China
Category:Industrial Supplies / Construction Machine
Label:cement production li , Concrete
Price: -
Min. Order:-
Inquire Now

Product Description

Main process equipment for 1000 tons/day cement production line 

1, selection of limestone crushing PCD1612 single-section hammer crusher, calibration, 100-100 t/h, the grain-size < 300 mm, discharging granularity < 25 mm.System should be broken limestone 240732.76 tons, crushing 732.82 tons, daily work 8 hours, utilization rate of 30.00%, can meet the production requirements.
2, raw material drying need clay 16447.60 tons (dry), daily 50.07 tons.Choose a phi 2.2 mX16m dryers, production capacity of 7 t/h, daily work 8 hours, annual utilization of 30.00%, can meet the production requirements.
3, Raw meal grinding Raw meal completed the year after need 299592 tons of Raw mill, daily 912 tons of Raw materials.Choose a phi 2.6 mX10m circle flow mill, production capacity of 40-45 t/h, daily working hours 22 hours, annual utilization of 82.5%, can meet the production requirements.
4, after the completion of rotary kiln with an annual output of 197100 tons of clinker, 600 tons of clinker.Choose a phi 3.3 mX52m with 5-stage cyclone preheater kiln, production capacity of 25 t/h, daily working hours for 24 hours, annual utilization of 92%, can meet the production requirements.
5, cooler clinker production for 25 t/h, choose a phi 3.2 mX36m single cylinder cooling machine, production capacity of 28 t/h, and can meet the production requirements
6, coal grinding to be burnt coal 33507 tons (dry), daily 102 tons of coal.Choose a phi mX5.8 2.2 m steel ball coal mill, the production capacity of 27-35 t/h, 22 hours daily working hours, annual utilization of 82.5%, can meet the production requirements.
7, built the year after next to cement mill grinding cement 201204.97 tons, daily grinding cement 612.50 tons.Choose a phi 2.6 mX13m circle flow mill, production capacity of 27-35 t/h, daily working hours 22 hours, annual utilization of 82.5%, can meet the production requirements.Need packing cement 201204.97 tons, daily packing cement 612.5 tons.Choose two fixed double mouth packing machine, single machine production capacity of 30 t/h, daily work time is 11 hours, annual utilization of 41.25%, can meet the production requirements.

1000 t/d cement production line 1

Member Information

Shenzhen Yuhan Electro-Mechanic Co., Ltd
Country/Region:Guang Dong - China
Business Nature:Manufacturer
Phone:02595839
Contact:amin (manager)
Last Online:29 May, 2014